|
FAR 15.403-4
Requiring cost or pricing data (10 U.S.C. 2306a and 41 U.S.C.
254b).
(a)(1) The contracting officer must obtain cost or pricing data
only if the contracting officer concludes that none of the
exceptions in 15.403-1(b) applies. However, if the contracting
officer has sufficient information available to determine price
reasonableness, then the contracting officer should consider
requesting a waiver under the exception at 15.403-1(b)(4). The
threshold for obtaining cost or pricing data is $550,000. Unless
an exception applies, cost or pricing data are required before
accomplishing any of the following actions expected to exceed
the current threshold or, for existing contracts, the threshold
specified in the contract:
(i) The award of any
negotiated contract (except for undefinitized actions such as
letter contracts).
(ii) The award of a
subcontract at any tier, if the contractor and each higher-tier
subcontractor were required to submit cost or pricing data (but
see waivers at 15.403-1(c)(4)).
(iii) The modification of any
sealed bid or negotiated contract (whether or not cost or
pricing data were initially required) or any subcontract covered
by paragraph (a)(1)(ii) of this subsection. Price adjustment
amounts must consider both increases and decreases (e.g., a
$200,000 modification resulting from a reduction of $400,000 and
an increase of $200,000 is a pricing adjustment exceeding
$550,000). This requirement does not apply when unrelated and
separately priced changes for which cost or pricing data would
not otherwise be required are included for administrative
convenience in the same modification. Negotiated final pricing
actions (such as termination settlements and total final price
agreements for fixed-price incentive and redeterminable
contracts) are contract modifications requiring cost or pricing
data if -
(A) The total final price
agreement for such settlements or agreements exceeds the
pertinent threshold set forth at paragraph (a)(1) of this
subsection; or
(B) The partial termination
settlement plus the estimate to complete the continued portion
of the contract exceeds the pertinent threshold set forth at
paragraph (a)(1) of this subsection (see 49.105(c)(15)).
(2) Unless prohibited because
an exception at 15.403-1(b) applies, the head of the contracting
activity, without power of delegation, may authorize the
contracting officer to obtain cost or pricing data for pricing
actions below the pertinent threshold in paragraph (a)(1) of
this subsection, provided the action exceeds the simplified
acquisition threshold. The head of the contracting activity
shall justify the requirement for cost or pricing data. The
documentation shall include a written finding that cost or
pricing data are necessary to determine whether the price is
fair and reasonable and the facts supporting that finding.
(b) When cost or pricing data
are required, the contracting officer shall require the
contractor or prospective contractor to submit to the
contracting officer (and to have any subcontractor or
prospective subcontractor submit to the prime contractor or
appropriate subcontractor tier) the following in support of any
proposal:
(1) The cost or pricing data.
(2) A certificate of current
cost or pricing data, in the format specified in 15.406-2,
certifying that to the best of its knowledge and belief, the
cost or pricing data were accurate, complete, and current as of
the date of agreement on price or, if applicable, an earlier
date agreed upon between the parties that is as close as
practicable to the date of agreement on price.
(c) If cost or pricing data
are requested and submitted by an offeror, but an exception is
later found to apply, the data must not be considered cost or
pricing data as defined in 2.101 and must not be certified in
accordance with 15.406-2.
(d) The requirements of this
subsection also apply to contracts entered into by an agency on
behalf of a foreign government. [FAC 97-2, 62 FR 51224,
9/30/97, effective 10/10/97; FAC 97-20, 65 FR 60542,
10/11/2000, effective 10/11/2000; FAC 97-22, 66 FR 2116,
1/10/2001, effective 3/12/2001; Delay of effective date, 66 FR
14259, 3/9/2001, effective 5/11/2001]
Special
Note & Requirement for Anodized Parts
Acceptable
anodizing for Type I, II or III, Class 2, is the outcome of
processes that are controlled in accordance with strict
guidelines imposed by the plating dye/chemical supplier. These
processes shall be closely monitored, inspected and checked
during each step of the anodizing process by the plating
supplier.
DRS TEM
expects the machine shop to verify, confirm and validate that
the COC and anodizing processes of the sub-tier suppliers meet
the requirements as called out on the PO and drawings. DRS TEM
reserves the right to audit all sub-tier suppliers.
DRS TEM
requires a certificate of conformance (COC) from the plating
supplier and supporting documentation for the anodizing when
requested. A COC shall be provided for each lot supplied by the
machine shop to DRS TEM. The COC from the plating supplier
shall be attached to the COC from the machine shop. All COC's
shall be signed by a company designated official responsible for
Product Quality.
The other note that has been added into NWP is entitled
7.2.2
for 7.1.2 Anodize and needs to be included on ALL
RFQ's and PO's for metal fab-to-print parts with anodize finish
that are generated from NWP and by the proposal group.
Substitution of Finish 7.2.2 in lieu of 7.1.2
For any
metal fab-to-print drawing that calls out "Finish 7.1.2 of
MIL-STD-171, dyed black. Dimensional limits apply after finish",
the supplier may substitute "Finish 7.2.2 of MIL-STD-171, dyed
black. Dimensional limits apply after finish." without having to
submit a DRS TEM Supplier Request for Deviation/Waiver form.
**Leadfree components are acceptable
EXCEPT
for Ball Grid Arrays (BGA)
and Fine Pitch (20 mil or
less). MFR-052 will be added to all BGA and Fine
Pitch parts which states:
"MFR-052 - MUST BE TIN/LEAD ONLY. THERE ARE NO APPROVED
SUBSTITUTES".
Note the
exception
of
gold finishes,
which must be labeled and approved on a part by part basis
prior to award
of Purchase Order. All Responses to RFQ's must state that the
part has a gold finish.
|